Purchase Order (PO) Manager

Maintain end-to-end operational control over overseas factory contracts. Track 30% advance deposits, schedule AQL quality inspection hold points, monitor production lifecycles, and authorize final balance payments safely.

Commercial Purchase Order (PO) Manager

Track supplier contracts, monitor 30/70 deposit & balance payment milestones, schedule quality inspection gates, and maintain end-to-end order accountability.

Showing 3 active purchase orders
PO NumberSupplier / VendorOrder DateTarget DeliveryTotal ValuePayment StatusOrder LifecycleActions

Best Practices for International Purchase Order Management

The 30/70 Milestone Payment Rule

In contract manufacturing, issuing payment without contractual leverage is the most common cause of commercial loss. The standard international payment protocol is:

  • 30% T/T Advance Deposit: Transferred upon PO countersigning to allow the factory to purchase raw materials and schedule tooling.
  • Quality Inspection Hold Point: When 100% of goods are produced and at least 80% are packed into export cartons, an independent inspection agency (e.g., QIMA, SGS, Bureau Veritas) performs an AQL Level II Pre-Shipment Inspection (PSI).
  • 70% Balance Release: Only authorized after receiving a passing PSI report with photographic evidence of carton drop-tests, dimensions, and functional compliance.

Essential Clauses on Every Export PO

A formal international PO is a binding commercial contract. Ensure your PO specifies:

  • Clear Delivery Milestone: The agreed Ex-Factory Date or Cargo Ready Date (CRD), with financial penalty terms for unauthorized production delays.
  • Exact Incoterm 2020: Designate the specific seaport (e.g., FOB Ningbo vs. EXW Factory) to prevent dispute over who pays domestic Chinese trucking and export customs clearance.
  • Quality Standard Reference: Explicitly state: "Goods must conform strictly to approved Golden Pre-Production Sample and achieve AQL 2.5 Major / 4.0 Minor defect tolerance."